European Nuclear Society
e-news Issue 21 Summer 2008
http://www.euronuclear.org/e-news/e-news-21/eurex.htm

SPENT FUEL POOL EMPTYING, DRAINAGE AND PURGING AT EUREX Plant (Italy)

By Costantino BIONDANI (biondani@sogin.it); Michele GILI (gili@sogin.it); Mara MOLLO (mollo@sogin.it)– Sogin Spa

Sogin EUREX Site, str. Crescentino I-13040 SALUGGIA (VC), Italy


At the beginning of 2004, some leakages from the spent fuel pool (SFP), a 675 m3 concrete basin, were discovered at the EUREX (Enriched Uranium Extraction) pilot reprocessing plant, which was in operation between 1970 and 1983.

Thin cracks in the pool wall caused leakages through the annular space of the pool and from there into the ground. Environmental analyses and radiological measures revealed the limited presence of Sr-90 radionuclide in upper water table samples.

In 2006, Sogin started not only transferring fuel to the nearby Avogadro Fuel Repository, but also draining and purging the pool.

The main steps of involved in this process are described as follows:

STEP 1: TRANSFER OF THE FUEL TO THE AVOGADRO FUEL REPOSITORY

Irradiated fuel (a total of 2 tonnes) from the Trino PWR, the Garigliano, according to the following strategy:

Fuel elements in SFP
Fuel elements in SFP

Duration: May-July 2007

STEP 2: RESTORATION OF WORKING AREAS

The maintenance of conventional and radiological safety was achieved by performing the following activities:

• The removal of 300 tonnes crane used for materials handling
• The transfer of AGN-1 cask and accessories from Trino NPP
• The restoration of grates and rails from SFP Area
• The removal of absorption frames used for moving cask AGN-1.

AGN-1 cask loading on trailer
AGN-1 cask loading on trailer

Duration: July 2007

STEP 3: REMOVAL FROM THE SFP OF SLIGHTLY CONTAMINATED DEVICES

This activity regards the removal of slightly contaminated devices, but not radiating, as for example:

• metallic 'clovers' not removed the previous year
• quivers containing Trino NPP elements and small baskets
• various devices used in the pool (rods, lamps, television camera)
• foot bridges used for quivers handling during loading fuel

Extraction of metallic ‘’clovers’’
Extraction of metallic 'clovers'

All the activities were performed according to operative procedures for fuel handling and radiation protection.

In particular, the phases involved in managing the waste were:

• the washing of waste in SFP Area
• the removal of waste from SFP Area
• the allocation of waste into appropriate containers
• the transfer to waste to the waste treatment company

Duration: September-November 2007

STEP 4: REMOVAL FROM THE SFP OF THE RADIATING COMPONENTS

This activity was the most relevant because it concerned the removal from the SFP of radiating components, such as the headstock MTR (Material Testing Reactors) elements and the magnox capsule.

An Operational Plan was written for the Italian Safety Authority and appropriate shielding and handling frames were designed in order to respect all the laws and regulations for transport and radiation protection.

Shielded containers for activated Headstock MTR

Shielded containers for activated Headstock MTR

Duration: December 2007; 1 week.

STEP 5: PRELIMINARY CLEANING ACTIVITIES OF SFP

These activities were performed by NUKEM Technology GmbH and ENERGY SOLUTIONS and consisted of the following phases of operational cleaning:


SIS removal

Duration: November 2007- February 2008; 2 months.

STEP 6: DISMANTLING OF PLANT COMPONENTS

This step consisted of removing and cleaning of plant components and frames that require special disassembly, for example the safety hydraulic System (SIS), the SFP bottom grids, pipes and metallic parts.

Duration: March 2008: 2 weeks.

STEP 7: SFP WATER PURIFICATION

The purification of the SFP water was performed by two different techniques:

  1. The Wall & Floor WasherTM technique, by NUKEM/ Energy Solutionsn, an outsourced service

    An underwater cleaning system was used to remove contaminated sludge from the EUREX SFP bottom: about 50 GBq of fission products and transuranic sludge were recovered.

  2. The Electrocoagulation process, called the SAFETM SYSTEM, by Energy Solutions, an outsourced service

    The water treatment was performed using ElectroCoagulation coupled with ultra-filtration and final polishing with ionic exchange resins. Water flow gets through the cells of the system and three chemical processes occur: coagulation, oxidation and aeration.

    Inside the ElectroCoagulation Unit (container ISO 20’) there are components for water treatment (settling, sludge and feed tanks) that allow the separation of the sludge from the water.


Internal Layout EC System


EC cells

Duration: March – June 2008: 4 months.

STEP 8: SFP WATER DRAINAGE AND DOWNLOAD

After accurate radiological monitoring (more than one hundred samples were analysed), water was gradually drained and transferred from the pool to the waste pond (a 1000 m3 external basin).

Surface radiological contamination was limited to pool walls by using specialised painting.

The final water downloading into the nearby Dora river required prior documentation presented to the Italian Safety Authority in order to justify the release levels.

Duration: June 2008: 1 month

ACTIVITY PLANNED

Additional steps are scheduled for the following activities:


© European Nuclear Society, 2008