| 

SPENT FUEL POOL EMPTYING, DRAINAGE AND PURGING
              AT EUREX Plant (Italy)By Costantino BIONDANI (biondani@sogin.it);
                
                Michele GILI (gili@sogin.it);
                
                Mara MOLLO (mollo@sogin.it)– Sogin
              Spa Sogin EUREX Site, str. Crescentino I-13040 SALUGGIA
                (VC), Italy  At the beginning of 2004, some leakages from the spent fuel pool
                (SFP), a 675 m3 concrete basin, were discovered at the EUREX
                (Enriched Uranium Extraction) pilot reprocessing plant, which
              was in operation between 1970 and 1983.
                 Thin cracks in the pool wall caused leakages through the annular
                  space of the pool and from there into the ground. Environmental
                  analyses and radiological measures revealed the limited presence
              of Sr-90 radionuclide in upper water table samples.                 In 2006, Sogin started not only transferring fuel to the nearby
                    Avogadro Fuel Repository, but also draining and purging the
              pool.                 The main steps of involved in
              this process are described as follows:  STEP 1: TRANSFER OF THE FUEL TO THE AVOGADRO
              FUEL REPOSITORYIrradiated fuel (a total of 2 tonnes) from the
              Trino PWR, the Garigliano, according to the following strategy:  
                
                   Reusing an AGN-1 transport cask with an internal
                    basket modification (6 elements for each cask; a total of
                  10 fuel transfers)
                   Loading the cask outside the water, designing a shielded shuttle
                  to move the fuel from the pool to the cask                 
                   Transferring the fuel to the nearby Avogadro Fuel Repository,
                              a short distance away (less than 1 km) reduced transport
          licensing duties.  Fuel elements in SFP
 Duration: May-July 2007 STEP 2: RESTORATION OF WORKING AREASThe maintenance of conventional and radiological safety was
              achieved by performing the following activities: • 
                The removal of 300 tonnes crane used for materials handling• 
                The transfer of AGN-1 cask and accessories from Trino NPP
 • 
                The restoration of grates and rails from SFP Area
 • 
                The removal of absorption frames used for moving cask AGN-1.
  AGN-1 cask loading on trailer
                 Duration: July 2007 STEP 3: REMOVAL FROM THE SFP OF SLIGHTLY CONTAMINATED DEVICESThis activity regards the removal of slightly contaminated devices,
              but not radiating, as for example: • metallic 'clovers' not removed
                the previous year• 
                quivers containing Trino NPP elements and small baskets
 • 
                various devices used in the pool (rods, lamps, television camera)
 • 
              foot bridges used for quivers handling during loading fuel
  Extraction of metallic 'clovers'
 All the activities were performed according to
              operative procedures for fuel handling and radiation protection.                 In particular, the phases involved in managing the waste were: • 
                the washing of waste in SFP Area• 
                the removal of waste from SFP Area
 • 
                the allocation of waste into appropriate containers
 • 
              the transfer to waste to the waste treatment company
                 Duration: September-November 2007    STEP 4: REMOVAL FROM THE SFP OF THE RADIATING
              COMPONENTS This activity was the most relevant because it
              concerned the removal from the SFP of radiating components, such
              as the headstock MTR (Material Testing Reactors) elements and the
              magnox capsule.                 An Operational Plan was written for the Italian Safety Authority
                and appropriate shielding and handling frames were designed in
                order to respect all the laws and regulations for transport and
              radiation protection. 
 Shielded containers for activated Headstock MTR
                 Duration: December 2007; 1 week. STEP 5: PRELIMINARY CLEANING ACTIVITIES OF SFPThese activities were performed by NUKEM Technology
              GmbH and ENERGY SOLUTIONS and consisted of the following phases
              of operational cleaning: 
                              
                the extraction of various devices from the pool and
                  radiological cleaning and packaging                
                 the sucking out of waste and sludge from the pool
                  bottom                
                 sediment materials recovery from the bottom and the
                  walls of the pool   SIS removal
 Duration: November 2007- February 2008; 2 months. STEP 6: DISMANTLING OF PLANT COMPONENTSThis step consisted of removing and cleaning of plant components
              and frames that require special disassembly, for example the safety
              hydraulic System (SIS), the SFP bottom grids, pipes and metallic
              parts.                 Duration: March 2008: 2 weeks.                 	STEP 7: SFP WATER PURIFICATIONThe purification of the SFP water was performed by two different
              techniques: 
                               
                The Wall & Floor WasherTM technique,
                  by NUKEM/ Energy Solutionsn, an outsourced service
 An underwater
                  cleaning system was used to remove contaminated
                            sludge from the EUREX SFP bottom: about 50 GBq of
                      fission products and
                transuranic sludge were recovered.
                
                 The Electrocoagulation process, called the SAFETM SYSTEM, by Energy Solutions, an outsourced service
 The water treatment was performed using ElectroCoagulation
                      coupled with ultra-filtration and final polishing with
                    ionic exchange resins.
                        Water flow gets through the cells of the system and three
                      chemical processes occur: coagulation, oxidation and aeration.
 
 Inside the ElectroCoagulation Unit (container ISO 20’)
                        there are components for water treatment (settling, sludge
                        and feed tanks)
                  that allow the separation of the sludge from the water.
                   Internal Layout EC System
  EC cells
 Duration:
                    March – June 2008: 4 months. STEP 8: SFP WATER DRAINAGE AND DOWNLOADAfter accurate radiological monitoring (more than one hundred
                    samples were analysed), water was gradually drained and transferred
              from the pool to the waste pond (a 1000 m3 external basin).                     Surface radiological contamination was limited to pool
              walls by using specialised painting.                     The final water downloading into the nearby Dora river
                        required prior documentation presented to the Italian
                        Safety Authority
              in order to justify the release levels.                     Duration: June 2008: 1 month ACTIVITY PLANNEDAdditional steps are scheduled for the following activities: 
                    
                       A SURVEY OF THE CONTAMINATION LEVEL OF THE ANNULAR
                      SPACE Radiological characterisation of the annular space, pool
                      frames and ground below the pool will be carried out
                       THE CONDITIONING AND TREATMENT OF WASTE ACTIVITIESAn outsourced service for the conditioning and treatment
                      of waste, in particular sludge and resins, will be used.
 
 
 |