| 

Ansaldo  NES – Silo Emptying Plant Mobile CavesThe MSSS facility at Sellafield was  built just over 50 years ago as a facility for the underwater storage of Magnox  swarf. This swarf was generated from Magnox fuel de-canning operations and a  variety of other intermediate level solid wastes, termed miscellaneous  beta-gamma waste (MBGW). Over the last 50 years, increased storage demands have  seen the silo extended three times to give a total of 22 storage compartments.  The operating floor of the building forms the roof of the compartments and  spans all four parts of the building. Above the silos, a shop floor gave access  to charge holes through which waste was deposited and is stored underwater.  
 In June 2015, Ansaldo NES, fully owned  by Ansaldo Nucleare and part of the Ansaldo Energia Group, achieved another  important milestone for Sellafield Ltd, completing, at the Wolverhampton site, the  testing and commissioning of the first of three Silo Emptying Plant (SEP)  mobile caves. The SEP machine has been dismantled into almost 30 separate  modules and transferred to the Ansaldo NES Beckermet facility, three miles from  the Sellafield main gate entrance, waiting to be reassembled inside the Magnox  Swarf Storage Silos (MSSS) building and tested before initiating solid waste  retrievals in 2017. .jpg)
 The MSSS building at Sellafield is one  of the site’s four Legacy Pond and Silo facilities and has been described as  one of the most challenging industrial decommissioning projects in Europe. The  Nuclear Decommissioning Authority (NDA) and Sellafield Ltd are focused on  safely decommissioning these buildings as part of the hazard and risk reduction  programme. Since 1996, Ansaldo NES (then owned by  Rolls-Royce) have been working with Sellafield Ltd on a project to design,  manufacture, test and commission a bespoke solution to resolve this challenge.  Three SEP machines are currently being constructed, tested and trialled by  Ansaldo NES at Wolverhampton and are at varying phases of their lifecycle. Each  of the fully assembled SEP Caves weights approximately 500 tonnes with  dimensions of 11m x 5m x 6m and is assembled from over 13,500 parts each. These  machines will be used to extract Intermediate Level Waste (ILW) from these compartments  ready for transfer and processing.   The  SEP machines will have to operate in a radioactive environment where operator  access is restricted due to the radiation dose levels.  Because of this, the machines will need to  work safely and continually for up to 25 years without any modifications or  upgrades. The SEP mobile caves are shielded cells that control a suite of waste  retrieval tools and equipment. The tools are deployed, as required, to  retrieve, re-size, reduce and consign to skips, the waste stored in each of the  silos. The SEP machines are mounted on a substantial rail system, allowing them  to be moved between silos as the retrievals operations progress. The exported  skips will then be transferred to the future new facility, the Sellafield Direct  Encapsulation Plant (SDP), for further processing and immobilisation of the  waste. Ansaldo  NES is delivering to the MSSS programme with a dedicated Integrated Project  Team, deployed across its headquarters in Wolverhampton as well as sites in Risley  (Warrington) and Beckermet (Cumbria). Pro/Engineer 3D solid CAD modelling has  been used extensively during the design process to allow design iterations with  automatic updating of General Arrangement and Detailed Drawings. The final  models are some of the most complex that have been produced using the ProE  tool.   The  ProE software has the advantage that it provides virtual prototypes which identify  any design interface problems prior to manufacturing, thereby avoiding  unnecessary re-work. Produced to support the 3D solid CAD modelling was a  1/10th scale model of the retrievals process. This model was used to validate  and trial the effectiveness of various end effectors on the Second Stage  Deployment arm and also to identify rope twist and wear issues. The  concept of the shielded cell can be simply described as a shielded box with  tunnel and access penetrations to enable an operator to remotely control the  retrievals operation without being exposed to radiation or contaminated  material. The tools used to remove the waste itself have been designed and  developed specifically for the retrievals process.  To  meet the unique challenge of the retrieval operation, innovative bespoke  tooling has been developed by Ansaldo NES and is evident in numerous areas of  the SEP Mobile Caves. .jpg)
 Innovative  Design                  A  critical part of the design requirement was to ensure craters are not formed  within the compartments being excavated. Additional structural constraints  meant that the charge hole has a small aperture size through which all waste  must be retrieved and the necessity to keep track of the positioning and  rotational location.                 In order to achieve the operational  constraints, two important stages to the removals process were required. At the  beginning of retrievals, a grab is used to retrieve waste near the charge hole  and a solution was required to ensure that this would not result in the  formation of craters. Ansaldo NES developed a ‘silo rake’ with the ability to  form a flat bed of waste throughout the lifetime excavation of each silo  compartment. Telescopic rake arms consisting of a series of rectangular  sections that slide within each other on bearing pads were created using a  serapid chain to extend and retract the arms. It also features a slewing  mechanism, allowing the rake to rotate incrementally in relation to the top  plate assembly. Early  design of Telescoping Silo RakeAfter  the waste is removed from the upper section of the silos, a more direct approach  is employed which removes the need for the rake and increases the efficiency of  the retrieval process. Engineers at Ansaldo NES developed the Second Stage  Deployment (SSD) unit, able to deploy a ‘rope hung grab’ to a multitude of  predefined positions within the silo compartment.  A system, using two deployment arms to rotate  and extend from 1.2m to 3.3m in a controlled manner within a tightly controlled  space-envelope, allows all areas of the compartment to be accessed. The arms  are able to deploy a minimum mass of 410kg through their full range of travel  whilst managing the hydraulic supply hoses and maintaining a constant tool  height within ±50mm while in motion.                 Able  to deploy to four ‘rope hand-over’ positions with the use of bespoke end deflectors  and having the ability to park in a position to allow unhindered waste  retrieval operations. Significant time and cost was saved  during the design stages by the innovative use of a 1/10th scale 3D model,  able to simulate the behaviour and operation prior to full manufacture. This enabled  the design process to be accelerated and directly interfaced with finite element  analysis (FEA), for stress, seismic and impact assessments. Ansaldo NES  undertook comprehensive verification of the results using a variety of  alternative calculation methods to achieve this correlation.   |